New construction septic systems in Augusta come into the plan wherever the sewer does not reach the lot. Here is the order the work happens in, how big the tank has to be, and what Augusta's ground does to the plan.

Mini excavator installing a septic tank behind a new house in Augusta, GA

What does it take to put septic on a new Augusta homesite?

A new house on a lot without sewer needs a soil evaluation, a construction permit from the Richmond County environmental health office, a system sized to the bedroom count, and an inspection before anything is covered. Get the soil logged before the house is staked, since the best field ground often decides where the foundation can sit.

Before you plan around septic at all, ask Augusta Utilities whether a sewer main serves the parcel. Tying in may be the cheaper path, or it may not be offered at that address.

This page covers new construction for a site-built home. For a manufactured home see mobile home septic. For an existing house with a failing system see septic tank replacement.

Three drain field lines and a header beside a new home in Augusta, GA
Field lines beside a new build
Skid steer grading a cleared lot for a septic system in an Augusta, GA neighborhood
Lot graded before layout

What happens first, second and third?

Soil first, permit second, house pad third. Builders who reverse that order end up moving foundations or paying for a pumped system they did not need.

  1. Pick two possible field areas

    Before you settle the house footprint, we look for the highest, best drained ground away from wells and creeks. A second area helps if the first fails.

  2. Soil evaluation

    Georgia's Rule 511-3-1-.03(7) requires soil evaluations to be done by individuals certified by the Department. The classifier digs or bores and logs each layer.

  3. Permit application

    The county reviews the soil report, the bedroom count and a site plan. Under Rule 511-3-1-.03(3), a permit is issued only after a site inspection shows favorable soil, absorption and groundwater findings.

  4. House pad and rough grading

    Now the builder can set the pad, keeping equipment off the marked field area.

  5. Installation

    Tank, building sewer, distribution box and field, laid to the depths on the permit.

  6. Final inspection, then backfill

    Rule 511-3-1-.03(4) says no one may backfill or use the system until the final inspection is done.

How big does the tank need to be for a new house?

For a single-family home, Georgia's minimum is 1,000 gallons for one to four bedrooms, plus 250 gallons for each bedroom over four, plus 50 percent if the kitchen has a garbage grinder. Use the calculator below with your floor plan.

Tank size calculatorRule 511-3-1-.05(3)
How many bedrooms will the house have?

Pick a bedroom count to see the state minimum tank size.

That figure comes from Rule 511-3-1-.05(3). It is a floor, not a design. The field is sized separately from the soil report, and the county can require more when site conditions call for it. If you are on the fence about a fifth bedroom, size for it now. Adding capacity after the fact means digging up the yard.

Precast concrete septic tank lowered on chains into a sandy excavation in Augusta, GA
A 1,000 gallon class tank on chains
Concrete septic tank lids and outlet line to a distribution box in Augusta, GA
Tank lids and outlet line

What does Augusta soil do to a new system?

It decides the field type and length. Deep, dry sand usually takes water readily. Red clay takes it slowly. Stream terrace soils near creeks can hold a high water table for months at a time.

The Augusta soil series, found on stream terraces in the Piedmont and Upper Coastal Plain, is somewhat poorly drained, with a seasonal high water table 12 to 24 inches down from December through May. A homesite with that kind of soil may need a shallower field, more field area, or an alternative design. On sloping sandy ground, watch for the hillside seeps the USDA Sand Hills description mentions, wet from November through April.

None of that is a reason to skip a lot. It is a reason to know before you close. The soil evaluation page covers what the classifier looks for.

Four drain field lines laid in pale sandy soil at the edge of pine woods in Augusta, GA
Lines in pale sandy ground
Drain field trenches with bundled pipe cut into red clay in Augusta, GA
Trenches cut into red clay

Where can the tank and field go on the lot?

Where the soil is good and the state's minimum distances are met. Under Georgia's rules a tank sits at least 50 feet from a well and 10 feet from property lines; a drain field sits at least 100 feet from a well and 5 feet from property lines.

Ponds, lakes and streams push the tank back 25 feet and the field back 50 feet. A building with a basement needs 10 feet from the field. Those figures come from Rules 511-3-1-.05(2) and .07(3). The setback planner draws them to scale so you can test a spot before the surveyor stakes the house.

Count a neighbor’s well, too. The rule applies to existing or proposed wells, not only yours.

What goes into a new construction estimate?

Each piece of the job as its own line: tank, field, distribution box, building sewer from the house stub, any pump tank and alarm, earthwork, and the permit and inspection steps. That is what we mean by a free itemized estimate.

Seeing it that way lets you compare bids honestly and spot the item that changed when the soil report came back. The cost factors page explains what moves each line.

New construction septic questions

Can I clear the lot before the septic permit is issued?
Be careful. Georgia's rules say no one may begin the physical development of a lot that will use septic until the county has issued a construction permit. Grading or parking equipment on the future field area can ruin the soil the permit depends on, so talk to us before the dozer shows up.
How many bedrooms should I tell the county?
The number the house will actually have, counting any bonus room that could be used as a bedroom. Tank size and field size follow bedroom count. A system permitted for three bedrooms is a problem if the house is sold as four.
Do I need a bigger tank for a garbage disposal?
Yes. Georgia's rules require the tank to be 50 percent larger when a garbage grinder will be used. On a three bedroom house that means 1,500 gallons instead of 1,000.
How long does installation take once the permit is in hand?
The digging and setting on a typical new house runs a few working days, weather allowing. The county inspection has to happen before backfill, so the calendar also depends on the inspector's schedule.
Can the builder pour the driveway over the field?
No. Georgia's rule says a septic tank should sit at least 10 feet from drives, pools, hardscape and foundations, and fields have their own distances. Driving over lines crushes them. We mark the field so the builder can work around it.
Who handles the soil evaluation?
A soil classifier certified by the Department of Public Health. We can line one up for you or work from a report you already have. See perc test and soil evaluation.